Pivka Solar Photovoltaic Station I and II

Sončna elektrarna v občini Pivka: SFVE TEP 1 - KAL in SFVE TEP 2 - KAL

On 1st July 2011, after all the required documentation had been obtained, the construction of the TEP-1KAL and TEP-2KAL Solar Power Station in the Pivka municipality began.

The TEP-1KAL and TEP-2KAL Solar Power Station is located at the Pivka poultry farm, in the Pivka municipality. It consists of 4,740 monocrystalline-silicon solar modules with a total peak power of 1,185 kWp, which are integrated into the roof covering of seven of the farm's facilities. Prior to the integration of the solar modules, the old and worn-out asbestos roof covering was replaced with a new one, which has built-in thermal insulation. The investor of the power station is the company TEP-SOLAR d.o.o.; its designer as well as the main contractor is TEP d.o.o.

According to the plan, the TEP-1KAL and TEP-2KAL Solar Power Station will be constructed by the end of the summer. Annually, it will generate approximately 1.4 MWh of electricity, which corresponds to the annual electricity consumption of 300 households. The Notranjska region will thus obtain a large solar power station, by means of which it will contribute to a cleaner environment.

   

Solar power plant Šenkinc

Sončna elektrarna Šenkinc

Šenkinc Solar Power Station in Ilirska Bistrica, 49.5 kWp, roof-integrated

The Šenkinc Solar Power Station is located on the roof of the warehouse of the wholesale company Šenkinc d.o.o., in Ilirska Bistrica. It consists of nearly 200 solar modules – they are the generator of the power station – which are integrated into the roof covering with an insulation thickness of 3 cm. The power station has a peak power of 49.5 kWp. Annually, it will generate 50 megawatt-hours of electricity and thus cover the annual electricity consumption of 12 Slovenian households. The power station is connected to the public electricity grid of Elektro Primorska.

The investor, Šenkinc d.o.o., had the power station constructed on a turnkey basis. From designing the power station, obtaining the required consents, approvals as well as permits, and supplying material with the appropriate certificates, to constructing the power station, connecting the power station to the public electricity grid, and obtaining the declaration for the production facility as well as a grant – TEP d.o.o. arranged everything for the project idea to come true.  

Telefon: 059 948 556

 

Spremljanje delovanja elektrarn >>

 

 

Avtomatizacija strojev in naprav za industrijske procese. >>

 

Copyright © 2010, TEP d.o.o., sončne elektrarne
Staro selo 2c, 5222 Kobarid, Tel.: 05 994 85 56, info@tep.si
Izvedba: TEP